BEREKETLİ WPP (32 MW)
154kV Transformer Substation, Power Transmission Line and MV WPP Electrical Construction Works:
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
Civil Works: All required civil works for SS, MV cable trenches and OHL
Electrical Works: 154kV 1272 MCM Conductor Transmission Line and 154/34,5 kV BEREKETLİ WPP Substation, WPP MV Electric Distribution (Power Distribution Line and Cable),
*Supply, delivery, installation of electrical, electromechanical equipment/material (except turbines)
*test and commissioning ( except turbines )
- EMPLOYER KİNESİS ENERJİ MADENCİLİK AKARYAKIT YAPI ENDÜSTRİSİ LTD.ŞTİ.
- StartJanuary 2015
- EndMarch 2016
- PlaceReşadiye/Tokat
- Total Installed Capacity of The Project32 MV
- Number of Turbines10
- Turbine Brand NameSiemens
- CATEGORY Completed Projects , Completed-Connection of Generation Plants to the Grid , Completed-Renewable Energy , Completed-Wind Power Plant
- TAGS Completed Projects , Completed-Wind Power Plant