BULANIK SUBSTATION (154 kV)
TEİAŞ İTM-70 REFERENCED TENDER 154 kV BULANIK SUBSTATION EXTENSION CONSTRUCTION
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
*Civil works
*Supply, delivery, installation
*test and commissioning
of electrical and electromechanical equipment/material of 154 kV Substation EXTENSION WORKS.
- EMPLOYER TURKISH ELECTRICITY TRANSMISSION COMPANY GENERAL MANAGEMENT
- StartSeptember 2011
- EndNovember 2012
- CATEGORY Completed Projects , Completed-AIS & GIS Transformer Substations , Completed-TEİAŞ Transmission System Construction Works
- TAGS Completed Projects , Completed-AIS & GIS Transformer Substations