BERGRES WPP (69,95 MW)
154kV Transformer Substation, Power Transmission Line and MV WPP Electrical Construction Works:
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
Civil Works: All required civil works for SS, MV cable trenches and OHL
Electrical Works: 154kV 5,32 km 2×1272 MCM Conductor Transmission Line and 154/34,5 kV BERGRES WPP Substation, WPP MV Electric Distribution (Power Distribution Line and Cable),
*Supply, delivery, installation of electrical, electromechanical equipment/material (except turbines)
*test and commissioning ( except turbines )
- EMPLOYER BERGRES ELEKTRİK ÜRETİM A.Ş. (DOST ENERJİ)
- StartMarch 2016
- EndJanuary 2017
- PlaceBergama/İzmir
- Total Installed Capacity of The Project 69,95 MV
- Number of Turbines22
- Turbine Brand NameGE