DENİZLİ DOĞALGAZ ŞALT (154 kV)
DENİZLİ 200 MW NG CCPP 154 Kv TRANSFORMER SUBSTATION AND OPPOSITE FEEDERS CONSTRUCTION WORKS AT TEİAŞ OPPOSITE TR.SUBSTATIONS
Description of supplied services by our Company under this contract:
*Design and engineering,
*Electrical and civil projects,
*Civil works,
*Electrical works: Supply, delivery, installation,
*test and commissioning of electrical and electromechanical equipment/material of 154kV Substation and opposite feeders at TEİAŞ Transformer Substations
- EMPLOYER AGE İNŞAAT VE TİCARET A.Ş.
- StartMarch 1, 2011
- EndMarch 1, 2012
- Total Installed Capacity of NG CCPP200 MW
- PlaceDenizli
- CATEGORY Completed Projects , Completed-Connection of Generation Plants to the Grid , Completed-Natural Gas Combined Cycle and Coal Power Plants , Completed-Thermal Power Plants
- TAGS Completed Projects , Completed-Natural Gas Combined Cycle and Coal Power Plants