GERES WPP (27,5 MW)
154kV Transformer Substation, Power Transmission Line and MV WPP Electrical Construction Works:
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
Civil Works: All required civil works for SS, MV cable trenches and OHL
Electrical Works: 154kV 6,5km 2×1272 MCM Conductor Transmission Line and 154/34,5 kV GERES WPP Substation, WPP MV Electric Distribution (Power Distribution Line and Cable),
*Supply, delivery, installation of electrical, electromechanical equipment/material (except turbines)
*test and commissioning ( except turbines )
- EMPLOYER GERES ELEKTRİK ÜRETİM A.Ş.
- StartNovember 2012
- EndDecember 2013
- PlaceAkhisar/Manisa
- Total Installed Capacity of The Project27,5 MV
- Number of Turbines11
- Turbine Brand NameNORDEX