ŞULE WPP SUBSTATION (154 kV)
154 kV ŞULE WPP SUBSTATION, WIND PARK AND 1x3x1272 MCM OHL CONSTRUCTION WORK
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
*Civil Works
*Electrical works: Supply, delivery, installation
*Test and commissioning of electrical and electromechanical equipment/material of 154 kV Substation, Wind Park, opposite SS Line Feeder and 154 kV 1x3x1272 MCM 19,09 km OHL
- EMPLOYER ŞULE ENERJİ ÜRETİM SANAYİ VE TİCARET A.Ş.
- StartSeptember 2023
- EndSeptember 2024
- PlaceISPARTA
- CATEGORY Ongoing Projects , Ongoing-Connection of Generation Plants to the Grid , Ongoing-Over Head Lines , Ongoing-Renewable Energy , Ongoing-TEİAŞ Transmission System Construction Works , Ongoing-Wind Power Plant
- TAGS Ongoing Projects , Ongoing-Connection of Generation Plants to the Grid , Ongoing-Over Head Lines , Ongoing-Renewable Energy , Ongoing-TEİAŞ Transmission System Construction Works , Ongoing-Wind Power Plant