TAHA SUBSTATION-OHL (154 kV-200 MW)
154 kV TAHA 200 MW NG CCPP SUBSTATION AND 2,3km TRANSMISSION LINE CONSTRUCTION WORKS
Description of supplied services by our Company under this contract:
*Design and engineering
*Electrical and civil projects
*Civil works
*Electrical works: Supply, delivery, installation,
*test and commissioning of electrical and electromechanical equipment/material of 154kV Substation and 154kV 2,3 km Transmission line with 1272 MCM Conductor
- EMPLOYER EVER ENDÜSTRİ A.Ş.
- StartJuly 1, 2014
- EndJanuary 1, 2015
- PlaceMardin
- CATEGORY Completed Projects , Completed-Connection of Generation Plants to the Grid , Completed-Natural Gas Combined Cycle and Coal Power Plants , Completed-Thermal Power Plants
- TAGS Completed Projects , Completed-Natural Gas Combined Cycle and Coal Power Plants