TÜRKERLER GPP-OHL (154 kV)
TÜRKERLER GPP-OHL TRANSMISSION LINES CONSTRUCTION WORKS
Description of supplied services by our Company under this contract: Construction of 154kV 4,07 km Transmission line with 2×1272 MCM Conductor
- EMPLOYER TÜRKERLER
- StartMay 2018
- EndSeptember 2018
- PlaceAlaşehir/Manisa
- CATEGORY Completed Projects , Completed-Over Head Lines , Completed-TEİAŞ Transmission System Construction Works
- TAGS Completed Projects , Completed-Over Head Lines