UZUNDERE SUBSTATION (154 kV)
3TM6- REF. 380 kV UZUNDERE SUBSTATION EXTENSION CONSTRUCTION
Description of supplied services by our Company under this contract: *Design and engineering
*Electrical and civil projects *Civil works *Supply, delivery, installation *test and commissioning of electrical and electromechanical equipment/material of 154 kV Substation’s Reactor Feeder EXTENSION WORKS.
- EMPLOYER TÜRKİYE ELEKTRİK İLETİM A.Ş. GENEL MÜDÜRLÜĞÜ
- StartNovember 1, 2018
- EndSeptember 1, 2019
- Placeİzmir
- CATEGORY Completed Projects , Completed-AIS & GIS Transformer Substations , Completed-TEİAŞ Transmission System Construction Works