YEŞİLYURT ENERGY SUBSTATION (154 kV)
Tuesday, 01 January 2013 by Güngör Elektrik
YEŞİLYURT ENERJİ SAMSUN OSB NG CCPP 154 kV SUBSTATION CONSTRUCTION AND EXTENSION WORKS AT OPPOSITE TEİAŞ TRANSFORMER SUBSTATIONS (SAMSUN I & SAMSUN III SUBS.)
Total Installed Capacity of NG CCPP: 132 MW
Description of supplied services by our Company under this contract:
*Design and engineering,
*Electrical and civil projects
*Civil works
*Electrical works: Supply, delivery, installation,
*test and commissioning of electrical and electromechanical equipment/material of 154kV Substation and opposite feeders